Do I need a permit for rooftop solar in Encinitas, and how does it work?

Roofing & Solarsolarpermitssolarappre-roof

We're thinking about rooftop solar, maybe with a battery. What permits does the City require, and is there a fast track?

Accepted answer
Encinitas Forum teamStaff

Yes, you need a City permit, and small systems get expedited review

Under state law (AB 2188), small solar systems get an expedited permit process. That means up to 10 kW for photovoltaic (PV) and up to 30 kW for solar water heating. Encinitas adopted Municipal Code Chapter 23.13 through Ordinance 2015-13 on August 19, 2015 [1].

How to apply

Applications go through the City's online Customer Self Service (CSS) portal. You'll need an eligibility checklist, standard plan, structural criteria, roof plan, elevation drawing and the manufacturer's specifications [1].

SolarAPP+ for instant permits

The City accepts PV-only and PV-with-battery permits through SolarAPP+. Main panel upgrades will be added later. To be eligible, a project must be on the rooftop of a permitted main residence (no ballasted or ground mounts), use a licensed contractor with an active City of Encinitas business license, and be outside the Coastal Bluff Overlay Zone. SolarAPP+ charges a $25 processing fee [2].

Separate permits

A re-roof needs its own permit [2]. Solar PV, batteries, main service panel upgrades and EV chargers each need a separate permit [3]. The City's solar application page links to a flyer about fee waivers or reductions for solar and EV charging permits [4].

Connecting to the grid

City approval doesn't authorize connecting the system to the utility grid. You need separate approval from the utility for that [5].